9. What events of force majeure give rise to relief? Must they be unforeseeable and to whom? How far does the express or implied allocation of risk under the contract affect whether an event qualifies? Must the event have a permanent effect? Is impossibility in performing required or does a degree of difficulty suffice? Is relief available where only some obligations (eg, to make a single payment or carry out one aspect of the works) are affected or is a greater impact required? What relief is available and does it apply automatically? Can the rules be excluded by agreement?
South Korea
Under Korean law, a force majeure defence might be accepted even if there is no express force majeure clause in the contract. This is on the basis of the general Korean law principle that obligor’s intent, wilful misconduct or negligence is required for contractual liability and in a force majeure situation it would be deemed that there was no intent, wilful misconduct or negligence on the part of obligor. As such, there is no specific limitation to types of force majeure events.
The Korean courts have determined that the force majeure event must be unforeseeable to a party seeking relief.
The risk of a force majeure event may be allocated between the parties by contract.
Permanency of effect is not an essential factor in Korean courts.
As noted above, the absence of intent, wilful misconduct or negligence in performance on part of the obligor is a prerequisite to recognising a force majeure event. Thus, in theory, relief is available even if performance is not objectively impossible (ie, can be done by a third party), but practically impossible from the obligor’s subjective point of view. However, in practice, the court tends to rarely allow a force majeure defence where there is no express force majeure clause in the contract.
The available reliefs are: (i) to be excused from the obligation(s) which are affected due to the force majeure event(s) (where only certain obligation(s) that are not material are affected); or (ii) to terminate the contract (where material obligation(s) are affected). Relief does not apply automatically. According to Supreme Court precedents, force majeure is a ground for limiting the liability of a contracting party that failed to perform its obligation and therefore, the burden of proof, in principle, lies with the party claiming force majeure.
Rules concerning force majeure can be excluded by agreement.
Answer contributed by
Byung-Woo Im,
Daewoong Lee and
Don Jeon
Kim & Chang