Contract formation
2. What are the requirements for a construction contract to be formed? When is a "letter of intent" from an employer to a contractor given contractual effect?
Japan
A contract is formed by an offer and an acceptance of specified terms. There are no particular formal requirements, although courts do require that key terms (such as price, date, etc) be sufficiently certain and supported by evidence. In principle, there is no requirement of “consideration” for a contract to be formed under Japanese law. The same principles apply to construction contracts.
As long as the above conditions for the formation of a contract are satisfied, a court will construe a ‘letter of intent’ as a contract regardless of its title. Otherwise, it will not be considered as a binding contract. It is possible for some terms to be found binding even if the whole is not.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Certifiers
5. When must a certifier under a construction contract act impartially, fairly and honestly? To what extent are the parties bound by certificates (where the contract does not expressly empower a court or arbitral tribunal to open up, review and revise certificates)? Can the contractor bring proceedings directly against the certifier?
Japan
Under the Building Standard Act (Act No. 201 of 1950, as amended), an employer of a large-scale construction must retain a certified architect as administrator for the project, whose role includes issuing certificates (and to this extent should be considered as a “certifier” in Japanese-law context). Under the Act on Architects and Building Engineers (Act No. 202 of 1950, as amended), such certifier must immediately inform a contractor of any deviation of construction works from the drawings or specifications and request amendment works. If a contractor fails to respond, the certifier must inform the employer. An architect owes a statutory duty to perform these duties fairly and honestly.
These two Acts are silent on whether the parties to a construction contract are bound by the determinations of the certifier. As to the potential liability of the certifier, in cases of exceptional negligence, a contractor could bring direct tort claims against the certifier.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Disruption
7. How does the law view "disruption" to the contractor (as distinct from delay or prolongation to the completion of the works) caused by the employer’s breaches of contract and acts of prevention? What must the contractor show for a disruption claim to succeed? If an entitlement in principle can be shown (eg, that a loss has been caused by a breach of contract) must the court or arbitral tribunal do its best to quantify that loss (even if proof of the quantum is lacking or uncertain)?
Japan
A contractor can assert a claim based on disruption. In principle, it would be like any other claim under contract or tort and the prospect of success will depend on particular facts and evidence in each case.
For a contractual claim, a contractor must prove the disruption was the result of a breach of contract by the employer, as well as demonstrate loss and the causation between the disruption and the loss. In cases where quantification of the loss is difficult for a contractor to prove, the Code of Civil Procedure (Act No. 109 of 1996, amended) confers on the court's discretion to determine a “reasonable amount” as damages taking into account the parties’ submissions and evidence.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Acceleration
8. How does the law view "constructive acceleration" (where the contractor incurs costs accelerating its works because an extension of time has not been granted that should have been)? What must the contractor show for such a claim to succeed? Does your answer differ if the employer acted unreasonably or in bad faith?
Japan
A contractor can assert a claim for ‘constructive acceleration’. In principle, it would be like any other claim under contract or tort and the prospect of success will depend on particular facts and evidence in each case.
To succeed on a breach of contract claim, a contractor must prove the ‘constructive acceleration’ was the result of a breach of contract by the employer as well as demonstrate loss and the causation between the ‘constructive acceleration’ and the loss. In this context, unreasonableness or bad faith by the employer may help a contractor to establish that the ‘constructive acceleration’ was a breach of contract by an employer.
In cases where quantification of the loss is difficult for a contractor to prove, the Code of Civil Procedure (Act No. 109 of 1996, amended) confers on the court's discretion to determine a “reasonable amount” as damages taking into account the parties’ submissions and evidence.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Force majeure and hardship
9. What events of force majeure give rise to relief? Must they be unforeseeable and to whom? How far does the express or implied allocation of risk under the contract affect whether an event qualifies? Must the event have a permanent effect? Is impossibility in performing required or does a degree of difficulty suffice? Is relief available where only some obligations (eg, to make a single payment or carry out one aspect of the works) are affected or is a greater impact required? What relief is available and does it apply automatically? Can the rules be excluded by agreement?
Japan
The concept of force majeure is recognised in the Civil Code (Act No. 89 of 1896, as amended) as a defence to a claim for damages where an event not attributable to the obligor has prevented performance of contractual obligations (other than payment of money). However, as there are very few cases in which the Japanese courts have upheld a force majeure defence, it is difficult to determine the parameters or requirements for whether a certain event constitutes a force majeure event. Rather, force majeure as a ground for release from contractual liability is usually subsumed in the termination of contract due to impossibility (article 542(1)(i) of the Civil Code) or of “no fault” (article 415 of the Civil Code) (ie, that the breach of contract was not attributable to the party who is alleged to be liable for damages).
It is not clear under Japanese law whether parties can contract out of the application of the force majeure principle in the Code as it is considered a core legal principle (although not much used in practice). It should also be noted that, while force majeure is a defence to liability, it is not a ground to terminate a contract. However, the impossibility of performance (for a reason that is not the fault of the terminating party) is a statutory ground for termination.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
10. When is a contractor entitled to relief against a construction contract becoming unduly expensive or otherwise hard to perform and what relief is available? Can the rules be excluded by agreement?
Japan
As a derivative of the principle of good faith under the Civil Code (Act No. 89 of 1896, as amended), the legal doctrine of ‘change in circumstances’ is potentially available as a defence to liability for non-performance in cases where there has been a fundamental change to circumstances from the time of entry of contract that strongly affects the fairness of the contract terms. This principle requires (i) a fundamental change was not foreseeable at the entry of the contract, (ii) the cause of which is not attributable to the parties, and (iii) that holding the parties to the original contractual terms would be harsh and against the principle of good faith.
It is unlikely that this doctrine could be excluded, as it derives from the principle of good faith, which is considered fundamental and mandatory. However, this doctrine is rarely applied and is considered to be highly dependent on the particular facts of individual cases. It could be possible to practically limit the application of the principle by explicitly allocating risks by contract, and thereby limiting the matters that were non-foreseeable.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Time bars
15. How do contractual provisions that bar claims if they are not validly notified within a certain period operate (including limitation or prescription laws that cannot be contracted out of, interpretation rules, any good faith principles and laws on unfair contract terms)? What is the scope for bringing claims outside the written terms of the contract under provisions such as sub-clause 20.1 of the FIDIC Red Book 1999 ("otherwise in connection with the contract")? Is there any difference in approach to claims based on matters that the employer caused and matters it did not, such as weather or ground conditions? Is there any difference in approach to claims for (a) extensions of time and relief from liquidated damages for delay and (b) monetary sums?
Japan
Contractual provisions that bar claims that were not notified to the counterparty within the specified period are effective. However, the court might interpret such provisions narrowly where public policy or the circumstances warrant it, such as in a consumer protection context. In such case, the effect of such provisions might be limited to the extent where an obligor can claim damages incurred for the failure to give due notice but cannot enjoy the waiver of the entire claim as stipulated in the contract.
Whether the contractual notification provisions are applicable to claims from outside of the contract depends on the interpretation of the said provisions and the importance of the nature of the relevant claims.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Omissions and termination for convenience
17. May the employer exercise an express power to omit work, or terminate the contract at will or for convenience, so as to give work to another contractor or to carry out the work itself?
Japan
Unless agreed otherwise by parties in a contract, an employer can terminate a contract at will or for convenience under the Civil Code (Act No. 89 of 1896, as amended) if the employer compensates any damage incurred by the contractor.
The Civil Code is silent on the issue of omission of work by an employer. However, if a contract has no express provisions that allow an employer to omit the part of work, it is likely that a Japanese court would hold that the contractor is entitled to claim damages including lost profits on the ground that such omission of work constitutes a breach of contract by the employer.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Termination
18. What termination rights exist? Can a construction contract be terminated in part? What are the practical and financial consequences?
Japan
Apart from termination rights provided in the contract itself, the Civil Code (Act No. 89 of 1896, as amended; the Code) provides certain statutory rights of termination. Such termination rights include (without limitation) (i) where a material breach has not been cured within a reasonable period after notice, (ii) where it is impossible to perform the contract, or (iii) where the other party repudiates the contract by indicating its intention not to perform its obligations. All such termination rights require that the terminating party is not at fault for the cause of termination.
The Code allows a construction contract to be terminated in part if an employer enjoys benefits from the parts that have been completed by a contractor and that are separable from non-complete parts. If a construction contract is terminated in part, a contractor is entitled to claim that portion of the contract price proportional or attributable to the completed works. The exception is that if an employer is liable for having a contractor impossible to complete construction an employer must pay all contract price to a contractor.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
19. If the construction contract provides for the circumstances in which each party may terminate the contract but does not expressly or impliedly state that those rights are exhaustive, are other rights to terminate available? If so, what are they and what are the practical and financial consequences?
Japan
A party can rely on statutory termination rights under the Civil Code (Act No. 89 of 1896, as amended), unless the construction contract excludes such statutory termination rights.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
20. What limits apply to exercising termination rights?
Japan
The exercise of both statutory and contractual termination rights would be restricted if the exercise of rights would be in conflict with the principle of good faith or constitute an abuse of rights, based on the specific facts of individual cases.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Completion
21. Does the law of your jurisdiction deem the works to be completed (irrespective of what the contract says) if, say, the employer takes beneficial possession of the works and starts using them?
Japan
Under the Civil Code (Act No. 89 of 1896, as amended), if a construction contract is terminated prior to the completion of the works or if the completion of the works becomes impossible, due to the causes attributable to an employer, the finished works are deemed to be completed, and the employer liable to compensate the contractor, to the extent that the employer enjoys the benefit of said works that is separable from unfinished works.
With regard to the completion of the whole works, the Code is silent. Under the case laws, the courts determine the completion of the construction works taking into consideration whether the process of construction works is finished in spite of the need to rectify defects or discrepancy from the contractual standard. In practice, the fact that an employer takes beneficial possession of the works can be used as evidence implying the completion of the works.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
22. Does approval or acceptance of work by or on behalf of the employer bar a subsequent complaint? What constitutes acceptance? Does taking over the work by the employer constitute acceptance? Does this bar subsequent complaint?
Japan
Under the Civil Code (Act No. 89 of 1896, as amended), irrespective of the acceptance of or taking over the works, an employer can claim its rights against a contractor for the breach of contract. Therefore, in general, the acceptance of or taking over the works does not constitute a waiver of employer’s rights or claims with respect to such works.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Liquidated damages and similar pre-agreed sums ('liquidated damages')
23. To what extent are liquidated damages for delay to the completion of the works treated as an exhaustive remedy for all of the employer’s losses due to (a) delay to the completion of the works by the contractual completion date; and (b) delays prior to the contractual completion date (in the absence of, say, interim milestone dates with liquidated damages for delay attaching to them)? What difference does it make if any critical delay is caused by the contractor’s fraud, wilful misconduct, recklessness or gross negligence? If so, what constitutes such behaviour and can it be excluded by agreement?
Japan
Under the Civil Code (Act No. 89 of 1896, as amended), provisions for liquidated damages – regardless of whether arising prior to or after the completion of the works – are generally interpreted as an exclusive remedy for damages, unless the parties explicitly agree otherwise (eg, by agreeing that actual damages could be claimed in addition to liquidated damages). However, liquidated damages provisions do not preclude parties from terminating the contract or claiming for specific performance.
It is uncertain whether the fact that a critical delay was caused by a contractor’s fraud, wilful misconduct, recklessness or gross negligence would affect these arguments due to the lack of case precedents.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
24. If the employer causes critical delay to the completion of the works and the construction contract does not provide for an extension of time to the contractual completion date (there being no "sweep up" provision such as that in sub-clause 8.4(c) of the FIDIC Silver Book 1999) is the employer still entitled to liquidated damages due to the late completion of works provided for under the contract?
Japan
In general, Japanese law requires the party to be “at fault” for it to be labile for breach. This applies even if liquidated damages have been agreed, unless it is clear that the parties have excluded the requirement of fault. Hence the contractor would not be liable for any liquidated damages if the employer causes a critical delay to the completion of works, even if there is no extension of time provision provided for under the contract.
Under such circumstances, the contractor would likely be excused from liability for delays that are not attributable to the contractor.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
25. When might a court or arbitral tribunal award less than the liquidated damages specified in the contract for delay or other matters (eg, substandard work)? What factors are taken into account?
Japan
Generally, a court or tribunal would uphold the amount of liquidated damages agreed by the parties in a contract. In exceptional circumstances, where the agreed amount of liquidated damage is contrary to the principle of good faith or against public policy, the courts can award less than the amount of liquidated damages under its discretion.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
26. When might a court or arbitral tribunal award more than the liquidated damages specified in the contract for delay or other matters (eg, work that does not achieve a specified standard)? What factors are taken into account?
Japan
As courts and arbitral tribunals would uphold the amount of the liquidated damages agreed by the parties in a contract, it would be very unusual for a greater amount of damages to be awarded. Depending on the specific facts of the case and wording of the liquidated damage provision, it might be possible to construe the provision narrowly so that actual damages could be assessed beyond the scope of such provision; this, however, is fact specific and cannot be generalised.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Assessing damages and limitations and exclusions of liability
27. How is monetary compensation for breach of contract assessed? For instance, if the contractor is liable for a defect in its works is the employer entitled to its lost profits? What if the lost profits are exceptionally high?
Japan
Japanese law recognises two categories of damages: ordinary damages and special damages. These categories of damages equally apply for breach of contract and tort. Ordinary damages are those that arise ordinarily and foreseeably from a breach of contract (or tortious act). Special damages relate to those arising from the unique circumstances of the case and are recoverable only if the party in breach should have foreseen such particular circumstances at the time of the breach (or tortious act).
Whether lost profits are considered as ordinary damages or special damages depends on the facts of the case. An exceptionally high amount of lost profits claimed by an employer might be rejected by the courts on the grounds of the lack of reasonable causation with the contractor’s breach of contract.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
28. If the contractor’s work is technically non-compliant, is the contractor liable for remedying it if the rectification cost is disproportionate to the benefit of the remedy? Can the parties agree on a regime that is stricter for the contractor than under the law of your jurisdiction?
Japan
Under the Civil Code (Act No. 89 of 1896, as amended), if the nature of non-compliance is not important and the rectification costs are disproportionate to the benefit of the remedy, the contractor does not have an obligation to rectify. An employer can claim damages only. Parties are generally free to agree on the stricter terms for a contractor than the statutory default position although the courts might intervene based on public policy or the principle of good faith.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
29. If there is a defects notification period (DNP) during which the contractor must or may remedy any defect in its works that appears during a certain period after their completion, if the construction contract is otherwise silent, does it affect the employer’s rights to claim for any defects appearing after the DNP expires?
Japan
Under the Civil Code (Act No. 89 of 1896, as amended), an employer is entitled to claim rectification, deduction from the contract price, damages and/or termination of contract within one year from the time that an employer acknowledges non-conformance in quality or types of the works.
Whether the said statutory rights of an employer is affected by the expiry of a DNP clause in the contract depends on the interpretation of the relevant contract provisions.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
30. What is the effect of a construction contract excluding liability for “indirect or consequential loss”?
Japan
Although the phrase “indirect or consequential loss” is not a term of art under Japanese law, a provision excluding such losses is generally construed as the exclusion of “special damages”. Such a contract provision is basically considered valid. However, if a breach of contract occurs by fraud, wilful conduct, or the reckless or gross negligence of the party in breach, the courts might intervene by implying a condition that the limitation of liability clause would not apply under those circumstances.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
31. Are contractually agreed limits on – or exclusions of – liability effective and how readily do claims in tort or delict avoid them? Do they not apply if there is fraud, wilful misconduct, recklessness or gross negligence: (a) if the contract is silent as to such behaviour; or (b) if the contract states that they apply notwithstanding such behaviour? If so, what causation is required between the behaviour and the loss?
Japan
Parties to a construction contract can agree on exclusion or limitation of liability for tort claims in addition to contractual claims.
In general, the courts are likely to restrict the application of such exclusion or limitation of liability provisions based on the good faith principle or public policy if the party in breach is found to be perpetuating a fraud, wilful misconduct, recklessness or gross negligence
The causation required between the behaviour and the loss follows that for the general principle of tort, which is reasonable causation between them.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Subcontractors
33. How do conditional payment (such as pay-when-paid) provisions operate under the law of your jurisdiction (including interpretation rules, any good faith principles and laws on unfair contract terms)?
Japan
“Pay-when-paid” provisions and similar conditional payment clauses are not prohibited under Japanese law. However, they must comply with the Construction Business Act (Act No. 100 of 1949, as amended) that require the main contractor:
- to pay the subcontractor within one month, and as soon as possible, from the date of receipt of the payment from the employer; and
- if they hold a licence as a “special construction business operator”, to pay within 50 days, and as soon as possible, from the date when the subcontractor demands taking over the works to the main contractor after the inspection of the said works.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
34. May a subcontractor claim against the employer for sums due to the subcontractor from the contractor? How are difficulties with the merits and proof of the subcontractor’s claim addressed, including any rights the contractor has to withhold payment? What if aspects of the project suggest that the law of your jurisdiction should not apply (eg, the parties to both the main contract and the subcontract have chosen a foreign law as the governing law)?
Japan
In general, a subcontractor cannot claim directly against an employer as there is no contractual relationship between them. However, if a subcontractor can prove a contractor is impecunious, the subcontractor can exercise a contractor’s right against an employer to claim payments and is entitled to receive direct payments from an employer.
It is unclear whether such a claim is permitted where both the main contract and the subcontract have chosen a foreign law as governing law. While there exists an old lower court judgment that affirmed its application as the rule of lex fori, it is uncertain whether this view will be followed by other courts.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
35. May an employer hold its contractor to their arbitration agreement if their dispute concerns a subcontractor (there being no arbitration agreement between the contractor and the subcontractor or no scope for joining two sets of arbitral proceedings) or can the contractor, for example, require litigation between itself, the employer and the subcontractor? Does it matter if the arbitration agreement does not have its seat in your jurisdiction?
Japan
An employer may hold its contractor to their arbitration agreement with respect to any dispute between the employer and the contractor, even if the dispute concerns a subcontractor who is not a party to the arbitration agreement. Under those circumstances, the contractor cannot require a litigation between itself, the employer and the subcontractor, as any dispute between the employer and contractor has to be referred to arbitration.
It is unlikely that the fact that the arbitration agreement provides for a foreign seat would affect this conclusion.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Third parties
36. May third parties obtain rights under construction contracts? How readily can those connected with the employer (such as future or ultimate owners) bring claims against the contractor in respect of (a) delays and (b) defects? To what extent are exclusions and limitations of liability in the construction contract relevant?
Japan
Generally, since contractual rights exist only between the parties to a construction contract, third parties will not obtain any rights under such construction contract unless such rights are expressly conferred on the third parties in the contract and the third parties show their intention to enjoy the benefit of the contract.
Under Japanese law, an employer can assign the entire contract or certain rights thereunder to a third party subject to not changing any rights for the contractor. Since the content of the rights will remain unchanged in such circumstances, the contractor can raise the same defences against such third party as it would have been entitled to raise vis-à-vis the initial employer, including exclusions and limitations of liability.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
37. How readily (absent fraud, wilful misconduct, recklessness or gross negligence) can those connected with the contractor (such as affiliates, directors or employees) face claims in respect of (a) delays (b) defects and (c) payment? To what extent are exclusions and limitations of liability in the construction contract relevant?
Japan
Parties connected with a contractor but who are not parties to the construction contract would generally not be subject to such claims by an employer. Except in instances of fraud, wilful misconduct, reckless or gross negligence, an employer can rarely bring a tort claim against parties connected with a contractor. Contract provisions pertaining to exclusions and limitations of liability are generally irrelevant to such tort claims against parties that are not parties to the construction contract.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Limitation and prescription periods
38. What are the key limitation or prescription rules for claims for money and defects (and insofar as you have a mandatory decennial liability (or similar) regime, what is its scope)? What stops time running for the purposes of these rules (assuming the arbitral rules are silent)? Are the rules substantive or procedural law? May parties agree different limitation or prescription rules?
Japan
Japanese law provides for:
- a five-year prescription period from the time when a creditor acknowledges that it is possible to exercise its rights; and
- a 10-year prescription period from the time when it is objectively possible for a creditor to exercise its rights.
Events that temporarily suspend the prescription periods include:
- filing a claim to the court;
- filing an application for enforcement to the court;
- a court order of interim measures including seizure of assets;
- a formal demand;
- parties’ agreement after the prescription period starts; and
- filing an arbitration proceeding.
Events that renew the prescription periods include:
- confirmation of rights by a final judgment;
- completion of enforcement procedures; and
- approval of rights by an obligor.
Prescription periods under Japanese law are considered to have a substantive legal effect. Where the prescription period has expired as to a claim, that claim would be extinguished.
Prescription periods are mandatory rules, and cannot be shortened or extended by party agreement before the prescription periods starts, though parties can agree to stay the running of the period.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Other key laws
39. What laws apply that cannot be excluded or modified by agreement where the law of your jurisdiction is the governing law of a construction contract? What are the key aspects of, say, the FIDIC Silver Book 1999 that would not operate as its plain words suggest?
Japan
Where Japanese law is the governing law of a construction contract, mandatory rules and laws cannot be contracted out of by party agreement. In general, mandatory laws are those pertaining to public policy such as competition laws and due process.
The FIDIC books are rarely used in domestic construction projects.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
40. What laws of your jurisdiction apply anyway where a foreign law governs a construction contract? What are the key aspects of, say, the FIDIC Silver Book 1999 that would not operate as its plain words suggest?
Japan
Even if the governing law of a construction contract is not Japanese law, mandatory rules and laws in Japan will apply within its territory. In general, mandatory laws are those pertaining to public policy such as competition laws and due process.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Courts and arbitral tribunals
42. Does your jurisdiction have courts or judges specialising in construction and arbitration?
Japan
The Tokyo and Osaka District Courts have specialised divisions for construction-related cases. There is currently no specific division in the Japanese courts specialising in arbitration-related cases. However, the Ministry of Justice is currently in the process of preparing a bill for the amendment of the Arbitration Act (Act No. 138 of 2003, as amended) that, if passed, will presumably confer on the Tokyo or Osaka District Courts concurrent jurisdiction in certain cases if the seat of arbitration is within Japan, the respondent has its domicile or office in Japan, or the subject of the claim or asset to be seized is within Japan.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
43. What are the relevant levels of court for construction and arbitration matters? Are their decisions published? Is there a doctrine of binding precedent?
Japan
As with most civil cases, the district courts and the summary courts have jurisdiction as the courts of first instance for construction-related cases, with the district courts handling claims above ¥1.4 million. For arbitration-related cases, the district courts have jurisdiction as the courts of first instance.
Save for cases conducted in private in accordance with relevant laws, all decisions rendered in Japanese courts are accessible to the public, and many but not all of them are published on the court website and/or by private service providers.
There is no general doctrine of precedent in the Japanese judicial system, but the conflict against a Supreme Court precedent may constitute the ground to file a petition for acceptance of a final appeal. As such, in practice, Supreme Court decisions have been respected as precedents by lower courts.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
44. In your jurisdiction, if a judge or arbitrator (specialist or otherwise) has views on the issues as they see them that are not put to them by the parties, can they raise them with the parties? Is the court or arbitral tribunal permitted or expected to give preliminary indications as to how it views the merits of the dispute?
Japan
While the Japanese court system applies the adversarial system in principle, under the Code of Civil Procedure (Act No. 109 of 1996, as amended) a presiding judge may independently ask questions even on issues not raised by the parties to clarify the issues. A judge may also give preliminary indications of the merits of the case, and it is not unusual for a judge to do so in order to encourage settlement in particular at the later stage of litigation.
For an arbitrator, there is no statutory restriction on raising questions and/or giving preliminary indications of the merits of the case during arbitral procedures.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
45. If a contractor, say, wishes to arbitrate pursuant to an arbitration agreement, what parallel proceedings might the employer bring in your jurisdiction? Does it make any difference if the dispute has yet to pass through preconditions to arbitration (such as those in clause 20 of the FIDIC Red Book 1999) or if one of the parties shows no regard for the preconditions (such as a DAB or amicable settlement process)?
Japan
If an employer initiates a lawsuit in Japanese courts contrary to the existence of the arbitration agreement, it will be dismissed without prejudice upon application by a contractor, unless: (i) the arbitration agreement is invalid; (ii) it is impossible to conduct arbitral proceedings; and (iii) the application was filed after a contractor submitted its argument on the merits of the case in arbitration. This is the case even while passing through contractual preconditions to arbitration or where the preconditions have not been satisfied.
If a tribunal finds its jurisdiction despite a contractor’s failure to take necessary steps required as preconditions to arbitration, an employer can apply to the courts within 30 days of the receipt of tribunal’s ruling for a review of the tribunal’s jurisdiction.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
46. If the seat of the arbitration is in your jurisdiction, might a contractor lose its right to arbitrate if it applied to a foreign court for interim or provisional relief?
Japan
The Arbitration Act (Act No. 138 of 2003, as amended) stipulates that an arbitration agreement will not refrain a contractor from filing a petition for an interim or provisional order from a Japanese court. There is no reason to think that there would be any difference if such relief is sought in a foreign court having jurisdiction.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
State entities
48. Summarise any specific limitations or requirements that apply when the employer is a state entity or public authority (including, for example, public procurement rules, limits on rights to suspend or terminate, excluded lien rights and arbitrating – as well as enforcing an award – against such an employer).
Japan
If the employer is a public authority in Japan, the relevant statutory laws and regulations for public procurement apply. These laws and regulations ensure economic efficiency, as well as fairness between the suppliers and the general public.
A construction contract will be awarded through bidding procedures, which are general competitive bidding and designated competitive bidding. In an exceptional case under strict conditions, a construction contract might be awarded directly, without a bidding procedure.
There is no domestic legislation explicitly prohibiting enforcement of an arbitral award against Japanese public authorities.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Privilege
50. Does the law of your jurisdiction recognise "without prejudice" privilege (such that "without privilege" communications are privileged from disclosure)? If not, may it be agreed that a sum is payable if communications to try to achieve a settlement are disclosed to a court or arbitral tribunal?
Japan
Japanese law does not expressly recognise the concept of "without prejudice" privilege. However, in practice for international issues including international arbitration, the principle of without prejudice privilege as it relates to good-faith settlement efforts is widely recognised. Therefore, an arbitral tribunal seated in Japan would likely uphold it in an international arbitration case. In addition, parties can agree contractually to a non-disclosure agreement in which any breaching party must pay a sum to the other if settlement communications are disclosed to a court or arbitral tribunal.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
51. Is the advice of in-house counsel privileged from disclosure under the law of your jurisdiction? Is the relevant law characterised as substantive or procedural law?
Japan
As a general rule, Japanese law does not recognise the general concept of attorney-client privilege as admitted in common law. However, such carve-outs are generally not needed in Japanese civil procedure as the Civil Procedure Code (Act No. 109 of 1996, as amended) provides for the protection against the request for document production. For example, a party can withhold a document from disclosure if it contains information obtained by qualified professionals through the performance of their duties. Although there is no relevant case law, the Code itself does not explicitly exclude in-house counsel who holds a legal qualification in Japan from qualified professionals.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
Guarantees
52. What are the requirements for a guarantee under the law of your jurisdiction? Are oral guarantees effective?
Japan
A guarantee must be in writing or recorded in an electronic form. Otherwise, it will be invalid and unenforceable.
Besides, there are special rules for a guarantee where a guarantor is not a judicial person. First, a revolving guarantee that covers unidentified obligations within a certain specific scope must include the maximum amount of obligations, without which it is ineffective. Further, a guarantee or a revolving guarantee that covers the obligation which is incurred from a loan transaction for business must be preceded by production of a notarised document certifying a guarantor’s intention to bear guarantee obligations.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
53. Under the law of your jurisdiction, will the guarantor’s liability be limited to that of the party to the underlying construction contract, if the guarantee is silent? Can the guarantee’s wording affect the position?
Japan
Under the Civil Code (Act No. 89 of 1896, as amended), a guarantor’s obligation is limited to that of the principal obligor.
In general, parties can broaden the scope of the guarantee by using a revolving guarantee that covers unidentified obligations within a certain specific scope. However, in such a case, parties should take note of specific provisions in the law that protect guarantors who are not judicial persons if applicable.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
54. Under the law of your jurisdiction, in what circumstances will a guarantor be released from liability under a guarantee, if the guarantee is silent? Can the guarantee’s wording affect the position?
Japan
It depends on the scope of the guarantee, for which the Japanese courts will seek to determine the guarantor’s real and actual intentions at the time of the provision of the guarantee, primarily with reference to the wording of the guarantee.
Based upon the Supreme Court decision (Case No. 126 (O) of 1971), for example, absent exceptional circumstances, a guarantor who provided an employer with a guarantee for a contractor will be deemed to agree to bear responsibility as a guarantor even for repayment of an advance payment that an employer will claim after terminating a construction contract on the grounds of a contractor’s breach of contract.
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
On-demand bonds
55. If an on-demand bond is governed by the law of your jurisdiction on what basis might a call be challenged in your courts as a matter of jurisdiction as well as substantive law? Assume the underlying contract is silent on when calls may be made.
Japan
A call of an on-demand bond governed by Japanese law will be subject to the principle of good faith and the prohibition of abuse of rights, both of which are provided for in the Civil Code (Act No. 89 of 1896, as amended).
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune
56. If an on-demand bond is governed by the law of your jurisdiction and the underlying contract restrains calls except for amounts that the employer is entitled to (such as sub-clause 4.2 of the FIDIC Red Book 1999), when would a court or arbitral tribunal applying your jurisdiction’s law restrain a call if the contractor contended that: (i) the employer does not have an entitlement in principle; or (ii) the employer has an entitlement in principle but not for the amount of the call?
Japan
There are no specific statutory laws or published court decisions with regard to the restraint of a call in such circumstances. The Japanese courts will interpret the relevant wording of an on-demand bond taking into consideration the commercial custom to find the parties’ real and actual intentions at the time of provision of such on-demand bond.
A call will be subject to limitation due to abuse of rights or contravention of public policy under the Civil Code (Act No. 89 of 1896, as amended).
Answer contributed by
Aoi Inoue,
David MacArthur,
Masahiro Yano and
Tatsuhiko Makino
Anderson Mōri & Tomotsune