Quantum in Oil and Gas and Mining Disputes

This is an Insight article, written by a selected partner as part of GAR's co-published content. Read more on Insight

Introduction

Natural resources development occurs in a highly globalised environment. As noted by the United Nations Conference on Trade and Development (UNCTAD) in its analysis of cross-border project finance transactions, ‘[m]ining is the most international industry, as more than half of all projects are sponsored by foreign companies, followed by oil and gas’.[2] For example, although the value of production from Canadian mines accounts for less than 4 per cent of global industry output,[3] nearly half of the world’s publicly traded mining companies are listed on Canadian exchanges.[4] The global investment patterns for these industries create frequent international disputes, both investor-state and commercial, involving large damages claims.

Resource extraction projects are heavily intertwined with governments. Concessions often are acquired from governments, development requires permits issued by governments and state-owned companies often participate in projects. The potential for allegations of government interference is significant and many projects in this sector have been political flashpoints. The value of these projects can be very large, particularly after up-front investments to develop the project have been completed. Moreover, their value can increase suddenly and substantially when results from exploration activities or shifts in commodity prices are favourable.[5] These circumstances create many opportunities for actual or perceived illegal actions by governments in the form of concession termination, state harassment, denial of permits, windfall taxes, royalty disputes, regulatory changes and even nationalisation. In some cases, states themselves seek counterclaim damages for claimant acts that are alleged to have harmed the value of the concession and the environment.[6] The high potential for disputes is borne out in case statistics, with extractive sector cases accounting for about 15 per cent of known investment cases.[7]

Climate and environmental aspects are gaining a more important presence in international disputes in view of the focus on energy transition, climate law obligations and environment protection. For instance, in Eco Oro Minerals Corp v. Republic of Colombia, the tribunal found Colombia liable for depriving the mining company of its right to operate within an environmental preservation zone. However, the tribunal decided that Colombia’s actions did not amount to an indirect expropriation because they were taken in good faith to protect the environment.[8] Similarly, Rockhopper Italia SpA et al. v. Italy revolves around the state’s environmental concerns and permits regarding an oil field near the coast, and its refusal to grant a production concession.[9] The tribunal found Italy’s actions amounted to an unlawful expropriation. This case adds to the debate about the Energy Charter Treaty (ECT), which is in the final states of its renewal process. The proposed update will align the ECT with the Paris Climate Accords and European Union environmental objectives.[10] The proposed update of the ECT could have a significant effect on fossil fuel investments. For example, it will allow parties to phase out the protection it provides to existing investments after 10 years. It will also limit the definition of ‘fair and equitable treatment’ and ‘indirect expropriation’ standards, carving out measures taken for the protection of public policy objectives, such as environmental protection. The proposed update would make it more difficult for investors to pursue claims against states.

Commercial activity in resource extraction creates significant potential for cross-border disputes between private parties. Investments are large and construction is often outsourced to contractors. The sector is often the subject of cross-border transactions[11] and joint ventures are a common way for even the largest companies to share risks. Projects also frequently involve long-term sales contracts with customers that may come out of balance over time and lead to disputes or arbitrated resets. Thus, the resource sector sees numerous commercial disputes, including disputes about construction, shareholder agreements, share purchase agreements and commodity sales agreements (e.g., take-or-pay and gas price disputes). For example, the London Court of International Arbitration disclosed that 25 per cent of the institution’s disputes were in the energy and resources sectors,[12] and International Chamber of Commerce data indicates that mining and energy accounted for 8 per cent and 10 per cent of its cases, respectively.[13] Recent curtailments by Gazprom of gas deliveries to Europe under long-term gas contracts based on force majeure claims are likely to give rise to future disputes.[14]

Figure 1, below, describes the typical life cycle of mining and oil and gas projects and some of the types of disputes that can arise. Companies begin prospecting to find candidate sites to explore. The exploration and development process follows, potentially marked by disputes about licences and permits. Once development is complete, construction begins, often giving rise to disputes between developers and construction contractors. During the operation phase, when producers are extracting and selling the reserves, disputes have often arisen about production taxes, royalty rates, changes in regulatory requirements and commodity sales contracts. Upon closure, potential disputes may arise about environmental remediation. At many stages of the process, assets may be subject to concession termination or nationalisation by governments, and commercial disputes may arise about joint venture and shareholder agreement and merger and acquisition transactions.

Figure 1: Disputes across extraction project life cycle

image-20221215102959-1

Many of these projects are especially large – one study identified 163 mega­projects (investment of more than US$1 billion) in the upstream oil and gas sector with an average size of US$6.6 billion.[15] The amounts at stake in arbitrations are correspondingly large, having resulted in the some of the largest awards on public record: eight of the 10 largest investment awards are in the extractive sector (Table 1, below), including the US$50 billion Yukos award, the largest on record.[16] Anecdotal evidence from commercial cases suggests similarly large amounts in play, such as the US$1.2 billion award in Vale v. BSG Resources.[17]

Table 1: Ten largest investment awards

 CaseAmount(US$ billions)Industry
1Yukos Investors v. Russia (three consolidated cases)50.0Oil and gas
2ConocoPhillips v. Venezuela8.4Oil and gas
3Tethyan Copper v. Pakistan4.1Mining
4Unión Fenosa v. Egypt2.0Downstream oil and gas
5Occidental v. Ecuador (II)1.8Oil and gas
6Mobil and others v. Venezuela1.6Oil and gas
7Caim v. India1.2Oil and gas
8Crystallex v. Venezuela1.2Mining
9Oschadbank v. Russia1.1Banking
10Rusoro Mining v. Venezuela1.0Mining

Other than the largest cases, extractive sector disputes often involve larger amounts than other industries. Table 2, below, shows the median amounts claimed and obtained by the investor (including through settlement) by industry, excluding cases in which no damages were awarded. In oil and gas, both claims and awards are approximately 10 times as large as the median non-extractive cases, with half of the cases involving claims of more than US$1 billion, and awards or settlements of more than US$380 million. In mining, median claims are also often significantly larger than those sought by claimants in other industries, but the amounts obtained are similar because awards in many mining disputes on early-stage projects have been based on historical costs incurred by the claimant.[18]

Table 2: Median claims and awards

 Median claim (US$ million)Median award (US$ million)
Oil and gas1,000380
Mining47219
Other industries12327

Important value drivers

Although there are many definitions of value, when used in the context of damages in international arbitration, value typically means fair market value (FMV). The FMV of a project is the price at which it would trade on the valuation date in an open market between willing and informed parties that do not act under any compulsion to trade.

Natural resource projects, like any productive assets, have value if they can generate future net cash flows with a positive present value. This value, therefore, is driven by factors that affect the magnitude, timing and riskiness of cash flows.

Unlike other business opportunities, natural resources are exhaustible, so total output depends on the size of the mineral or hydrocarbon deposit available for extraction. Deposit size cannot be known with certainty before extraction, so what matters for value are the estimates of size. In the extractive sector, these estimates are called resources and reserves. The terms mean different things in the oil and gas and mining industries but, generally, reserves are the portion of resources that can be extracted economically at current prices. The most frequently referenced definitions are published by the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) for mining and by the Society of Petroleum Engineers (SPE) for oil and gas.[19] Resources and reserves estimates are further classified based on geological uncertainty and confidence in commercial extractability. Figure 2, below, illustrates the CIM classification used in the mining industry.

Figure 2: Mining resources and reserves classification framework (CIM)[20]

image-20221219133952-1

Figure 3, below, is the SPE’s classification system for hydrocarbon deposits known as the Petroleum Resources Management System. Setting aside estimated unrecover­able amounts and prior production, the remaining deposit is considered to be the recoverable resource. It comprises reserves (proved, probable and possible) that are commercially recoverable, contingent resources that have a chance of being commercialised in the future, and prospective resources estimated to exist outside currently known accumulations with a chance of being commercialised.

Figure 3: Oil and gas resources classification framework (SPE)[21]

image-20221215103516-3

The size of the deposit determines a project’s duration and capacity. There is a trade-off between duration and capacity – a larger-scale project extracts the resource faster and generates higher revenues in present value, but requires higher up-front capital expenditures. One of the reasons why owners conduct detailed feasibility studies is to identify the scale that yields the highest value given expected prices and costs. Projects that end up in arbitration tend to be large in scale, requiring substantial up-front investments, and may have long expected lives, measured in decades.

Price expectations influence value directly and are typically the most important factor causing volatility in project values. Commodity prices can change rapidly, making the valuation date important and often itself a matter of dispute. Increased prices have been a factor causing governments to impose new measures on producers that lead to disputes.[22] For example, these effects have been especially large in expropriation cases, in which changing commodity prices during the period between the expropriation date (itself sometimes motivated by high prices) and the hearing date cause large differences in damages between the ex ante and the ex post framework.[23]

Extraction costs influence profitability and project value. They are determined by both project-specific and broader market factors. The project-specific factors include the quality of the deposit (e.g., ore grade, stripping ratio, amount of impurities and deposit depth), the method of extraction (e.g., open-pit versus underground in mining and conventional versus hydraulic fracturing in oil and gas), location (e.g., ease of access to key inputs such as water and power, transportation costs to market, weather disruptions and the effects on nearby communities or environmentally sensitive areas). The broader market factors include fuel costs, labour costs, equipment leasing rates and shipping costs.

Fiscal terms also affect profitability. In addition to corporate income tax, extractive projects often pay royalties to resource owners. Unlike income taxes, royalties are typically levied on the value of the product rather than the profits it produces. In many jurisdictions, the state owns all subsoil resources, making royalty rates a policy issue that generates political risk and can result in disputes.[24] State ownership gives rise to renewal risk when exploitation licences are expected to expire before resources are exhausted.

Country risk beyond fiscal terms is important. The value of otherwise similar projects can vary greatly depending on the stability of the political regime, the risk of expropriation, the strength of legal protections afforded to foreign entities, and the chances of civil war, terrorism and other forms of political violence. Some country risks arise from state acts prohibited by investment treaties and may be excluded from valuation for damages purposes in that context.[25]

Social and environmental risk can be critical to project value. Extractive projects affect the environment and the livelihoods of nearby communities to an extent that depends greatly on location, project design and the owner’s strategy of engaging with the community and civil society groups. Virtually all projects require environmental permits, and the process of acquiring permissions and licences is often lengthy and costly. The term ‘social licence to operate’ has come to embody a project’s ability to obtain the assent and support of a variety of stakeholders, beyond compliance with the formal permitting process. Failure to obtain the social licence to operate can lead to increased costs, delay and even project failure.[26] Social licence risk has increasingly come to the attention of arbitration tribunals and has been central to recent and ongoing cases. For example, the tribunal in Bear Creek Mining Corp v. Republic of Peru found that ‘there was little prospect for the Project to obtain the necessary social license to allow it to proceed to operation’,[27] awarding as a result sunk costs as damages.[28]

Valuation approaches

Valuation standards and guidelines

The three most common general approaches to valuation are known as income, market and cost. These approaches can be applied to energy and natural projects but their reliability depends on the information available. The amount of information is correlated to project stage, with earlier-stage exploration properties generally having less project-specific information than more advanced or producing assets.

Industry groups in countries with substantial extractive industries have developed valuation standards and guidelines. In Canada, for example, the CIM publishes the CIMVAL Code for the Valuation of Mineral Properties,[29] which imposes standards on valuation professionals and provides guidelines on methodology. The CIMVAL Code identifies which valuation approaches are generally considered appropriate for each project stage, shown in Table 3, below.[30] The same table is found in the Australasian VALMIN Code,[31] while South Africa’s SAMVAL Code provides more nuanced, but largely similar, recommendations and adds guidance for dormant and defunct properties.[32] For the oil and gas industry, the Society of Petroleum Evaluation Engineers provides valuation guidance.[33] The industry guidelines identify valuation approaches that are generally appropriate but do not require that any specific method be applied. The decision as to which method or methods to apply in any particular case is left to the valuer.

Table 3: Valuation approaches for different types of properties (CIMVAL Code, VALMIN)

Valuation approachExploration propertiesMineral resource propertiesDevelopment propertiesProduction properties
IncomeNoIn some casesYesYes
MarketYesYesYesYes
CostYesIn some casesNoNo

We discuss the income and market approaches below. The cost approach relies on the economic principle that, under normal conditions, a buyer will pay no more for an asset than the cost to obtain an equivalent asset.[34] The historical cost incurred may bear little resemblance to the current value for natural resources projects. Exploration begins with the implementation of techniques to identify prospects that look promising for further exploration and development. Therefore, the results of these exploration activities can cause the FMV to be materially higher or lower than the project’s historical cost, rendering the approach an unreliable means to make a claimant whole in most cases.[35]

Income approach

The income approach estimates the future cash flows that an asset can generate, adjusts them for timing and risk from the perspective of the valuation date and then adds them together to calculate the asset’s market value. By projecting directly the components that make up the asset’s cash flows, including anticipated production, prices and capital and operating costs, the income approach can take into account an asset’s unique characteristics.

The income approach is well suited to the valuation of natural resource projects.[36] The discounted cash flow (DCF) method was proposed in the majority of investment arbitrations with publicly available awards on damages, and was rejected by tribunals in favour of alternative valuation methods only in approximately one-third of those cases.[37]

Two principal factors contribute to the suitability of the income approach to resource extraction projects. First, the outputs produced by most oil and gas and mining projects are commodities. They sell in well-developed and liquid markets, often global in scope, with relatively little uncertainty about the producer’s ability to find buyers. Although commodity prices can be volatile, the existence of derivative markets – in which futures, forwards and options are traded – provides information that may allow the valuer to quantify price risk and develop objective, market-based price projections well into the future.[38] Futures and forward prices are the prices at which market participants today agree to exchange a unit of the commodity (e.g., a barrel of oil or an ounce of gold) at a known date in the future. They incorporate, therefore, the market participants’ expectations about the average price level in the future and the risk premium necessary to eliminate that risk. Forecasts prepared by professional forecasters may add additional information but must be carefully understood and interpreted.[39]

Second, large projects are undertaken only after the owners have conducted technical and economic assessments, such as feasibility and pre-feasibility studies and environmental impact assessments, which require detailed analyses of project viability. Once projects are in production, operators update production plans regularly to incorporate information developed during operations. These technical documents typically provide an objective basis to build projections of production and costs that incorporate the specific features of the asset being valued.

Valuing an asset by the income approach also requires directly quantifying the effects of risks on value. First, all risks should be factored into the cash flow, so that the projected net cash flows are expected values, in a statistical sense: they reflect what is anticipated to happen on average, considering the likelihood of both positive and negative outcomes.[40] Second, systematic risks require an additional adjustment to account for investors’ aversion to market risk.[41]

In the traditional DCF method, the adjustment for systematic risk takes the form of a risk premium added to the risk-free rate: assets that are subject to more systematic risk carry a higher premium. The higher the risk premium (and, hence, the discount rate), the larger the downward adjustment to expected cash flows and the lower the asset value, all else remaining constant.

A more sophisticated market-based DCF method, known as the certainty-equivalent DCF, can better incorporate the impact of systematic risk using market signals, when those are available. Rather than collapsing the adjustment for systematic risk into a single number, each cash flow stream (prices, capital expenditures and operating costs) is risk-adjusted individually, using the information provided by futures or forward prices.[42] By using futures prices for the value drivers sensitive to systematic risk,[43] in addition to accounting for all other risks in the same way as one would in the traditional DCF method, the resulting cash flows projections become certainty-equivalent cash flows. As the name suggests, these risk-adjusted cash flows are projections of what a market participant would be willing to accept at the valuation date in exchange for eliminating all risk. Having incorporated the effect of risk directly into the cash flows projections, the discount rate needs to reflect only the time value of money, for which the risk-free rate is appropriate. The Tethyan tribunal relied on this market-based DCF method to quantify damages from the expropriation of a copper-gold project at the feasibility study stage, noting its ability to reliably incorporate the effect of risk, its use and acceptance in the mining industry,[44] and its particular applicability to the circumstance of that case.[45]

Natural resource projects often have additional value from their ability to act as ‘real options’. Real options arise from management’s ability to adjust operations as economic circumstances change; examples include investing in capacity expansion when the price outlook is unexpectedly favourable, and mothballing or even terminating a project early, before resources are exhausted, when price declines make current production either unprofitable or less profitable than preserving the resources for future extraction in a more favourable price environment. The importance of real options varies across projects but is generally higher when prices and costs are more volatile, making large deviations from expectations (and, therefore, the need for changing course) more likely. The value of real options can be particularly significant in the oil and gas and mining sectors, in which volatility is common. The certainty-equivalent DCF method is the standard tool for estimating the value that optionality may add to a project.

Market approach

The economic theory known as the ‘law of one price’ dictates that comparable assets should transact at similar values.[46] The market approach leverages this principle, estimating the FMV of the subject asset based on observed prices from market transactions of comparable assets. Market values can be observed from share prices of publicly traded companies (traded comparables), which can be used to derive a company’s market value, or prices paid for comparable assets in transactions (comparable sales). Reliable use of the market method is preconditioned on identifying close comparables with observable market values, often a difficult task.

Valuation multiples from comparable assets

The most common application of the market method uses valuation multiples from comparable assets. Complex assets often have no perfect comparable because of size differences in profits or resource bases. To control for size, observed values are translated into multiples of financial measures (e.g., EBITDA multiples)[47] or deposit size (e.g., US$/barrel of oil). These multiples are applied to the relevant quantity (e.g., EBITDA or barrels) for the subject company, as illustrated below. Pre-production assets are generally valued using multiples of deposit size, while operating assets can be valued using earnings or cash flow multiples.

Figure 4, below, illustrates the method used to value an oil property. The observed US$1,000 FMV of the comparable asset is converted into a valuation multiple of US$40 per barrel of reserves. That multiple is then applied to the reserve base of the subject asset to derive its FMV. Because the subject asset is valued based on its size relative to the comparable asset, the multiples method is sometimes called relative valuation.

Figure 4: Illustration of comparables method for oil reserves

image-20221215103928-4

The appeal of multiples is its apparent simplicity. DCF valuations require one to develop explicit assumptions driving an asset’s cash flows. Relative valuation bypasses these explicit assumptions, instead relying on multiples derived from commonly available market data. The ease of implementation can be deceptive, because the use of a valuation multiple carries many strong, implicit assumptions that can undermine the method’s reliability.

FMV reflects market expectations about key aspects affecting the value of the asset. In the illustration above, the $1,000 observed value for the comparable asset would be a function of a variety of expectations about future project performance, such as those in Figure 5, below. Applying the $40 per barrel multiple in Figure 4, above, assumes that the subject asset is comparable in all these dimensions. Therefore, multiples analysis requires experts and tribunals carefully to assess comparability and the adjustments that attempt to account for differences.

Figure 5: Illustrative dimensions of comparability for extraction projects

image-20221215104053-5

Figure 6, below, presents a multiples analysis from an expert in a case on which the authors worked. The analysis identified 14 different projects deemed comparable. The resulting multiples covered a wide range, with the highest being 49 times larger than the lowest. The expert dropped the four highest and lowest multiples (light grey), leaving six multiples (black), with a more moderate implied valuation range. However, even within this narrowed set, the variation remains wide – the bottom of the range implies a value of US$100 million and the upper end is a value of US$220 million. More importantly, the multiples raise questions about comparability. Are these assets even comparable to each other, much less the subject asset? Why is it assumed that the subject of the valuation is like the middle range of the observed multiples, not the high? Or the low? Although this is a somewhat extreme case, wide multiples ranges are not uncommon and may suggest concerns about the comparability that must be evaluated to ensure a reliable outcome.

Figure 6: Observed multiples from transactions deemed comparable

image-20221219134154-2

Truly comparable assets can be difficult to identify. VALMIN explains that ‘[w]hilst widely used [comparables] are often flawed because companies are not truly comparable as risks and opportunities can be very different between compared projects/companies’.[48] Sometimes there are no good comparables. Even when reasonably comparable assets exist, it may be necessary to make adjustments to the multiple to account for differences. The reasonableness of these adjustments should be addressed in each case, and it is important that they do not mute the valuation signal that makes the market method useful.

In practice, multiples analysis has rarely been accepted by arbitral tribunals in mining disputes. Of 15 mining disputes that found on behalf of the claimant and for which awards are public, claimants in only six cases argued for the use of comparables.[49] The only investment arbitration we are aware of in which a tribunal adopted comparables as a primary valuation method is Crystallex, in which the tribunal accepted the claimant’s traded comparables analysis. The values of a set of publicly traded gold mining companies were converted into multiples of enterprise value per ounce of gold-equivalent reserves.[50] Although the tribunal recognised the existence of differences between Crystallex and the comparables, it found the differences were not large enough to prevent the use of the method.[51] The claimant also presented multiples for comparable sales trans­actions. The tribunal concluded that ‘in theory such method could yield reasonable results and would thus be an appropriate valuation method to value an investment in an international arbitration . . . [but] the Tribunal cannot consider it in this particular case’.[52] The tribunal found that differences would require adjustments that ‘are too plentiful to render this method of reliable value and that the assessment of damages reached through such calculations is too speculative to be taken into account’.[53]

The Gold Reserve tribunal relied primarily on a DCF analysis, because it was ‘not convinced that the comparables offered are sufficiently similar to enable them to be used in a weighted valuation calculation’.[54] However, the tribunal relied on comparables to find that the DCF submitted by the claimant’s expert was reasonable.[55] The other four tribunals disregarded the comparables methods because of a lack of comparability.[56]

Use of comparables is less common in upstream oil and gas disputes than in mining disputes. In Occidental v. Ecuador, the respondent argued for the use of comparables. The tribunal disregarded comparables and suggested that, more generally, in the upstream oil and gas industry, the uniqueness of each project makes the comparable sales method unreliable:

[T]he Tribunal agrees with the Claimants that “each oil and gas property presents a unique set of value parameters”. Therefore, the Tribunal concludes that it can derive no assistance from an analysis of the seven transactions which the Respondent has submitted as comparable sales.[57]

None of these tribunals disputed the validity of using valuation multiples; in fact, many explicitly recognised their legitimacy. The primary concern was the lack of reliable comparables.

P/NAV: A mining industry valuation method

The P/NAV multiple is a hybrid of the income and market methods sometimes used by mining equity analysts to value projects under development. ‘P’ is price, as measured by the market capitalisation of a publicly traded company and ‘NAV’ reflects the company’s net asset value, equal to the value of its assets minus its liabilities. The P/NAV ratio, therefore, reflects the market value of equity in a company relative to its NAV as calculated using a DCF model.

Analysts publish P/NAV multiples for mining companies, particularly those mining gold. In calculating these multiples, analysts will often populate their DCF analysis with generic rather than company-specific assumptions. For example, analysts may use a standard discount rate for all companies (often 5 per cent real); ignore country, social or environmental risk; assume a constant future gold price rather than rely on a forecast of expected gold prices; and make a particular assumption about how to account for the quality of resources and reserves.[58] Although this approach can be useful for facilitating comparisons across assets, the resulting NAV can differ from the company’s market capitalisation, creating a P/NAV ratio different from 1.0×.

To estimate the value of the subject project, its NAV is multiplied by the P/NAV ratio from comparable projects using the same approach illustrated for valuation multiples above. The P/NAV method has been applied by claimants in Crystallex and Gabriel Resources.[59] We are not aware of any tribunal that has made an award based on it.[60]

As with other valuation multiples, P/NAV multiples reflect the effects of risks (e.g., geological, permitting, technology, country and price) of the comparable projects. The method assumes that the risks of the project being valued are similar. Comparable assets, therefore, must be selected with careful attention to risk. Using P/NAV multiples from projects with different risk profiles will generate unreliable results. If the information is available to assess the comparability of risk, a DCF analysis may often be feasible and a better choice, given that the P/NAV method already requires sufficient information to generate cash flows projections and the DCF can better capture the unique aspects of a project.

Direct market evidence of asset’s value

In some cases, it is possible that an observed market value is available for the subject asset itself. It may be publicly traded or have been valued in a prior transaction. These values may provide objective information about its FMV and damages.

Share prices often represent an objective measure of market value. They can be used to estimate a company’s market capitalisation and enterprise value. The resulting valuation may be a reliable basis for estimating damages when the investment at issue is a large component of the claimant’s business, share prices reflect relevant and available information, there is no significant information not disclosed publicly, and it is possible to isolate the effects of alleged violations that give rise to the claims.

Tribunals have recognised the validity of information provided by a claimant’s own share prices. In Khan Resources v. Mongolia, the tribunal found this method to be more reliable than DCF and comparables:

The market capitalization approach advocated by the Respondents on its face has much attraction. The Tribunal accepts that Khan Canada ultimately held the investment that is the subject of this dispute and that it was essentially a ‘single-project’ company. The market capitalisation of Khan Canada should, therefore, reflect the market’s (i.e., a willing buyer’s) view of the value of the company and its interest in the Dornod Project . . . Absent countervailing factors, this should be the simplest and most accurate reflection of the value of the Claimants’ interest in the Dornod Project and is preferable to the approximations and estimations provided by the DCF and market comparables methodologies.[61]

Prior transactions in the subject asset may also provide evidence of an asset’s FMV. The tribunal in Bilcon v. Canada, a dispute about the proposed Whites Point aggregates quarry, relied on evidence from past transactions of the project itself:

In establishing the value of the opportunity lost by the Investors in the present case . . . the Tribunal has the benefit of being able to refer to certain past transactions made in relation to the Whites Point Project site, which allow it to establish an implied value range of the investment opportunity presented by the Whites Point Project, as it was seen by economic operators at different points in time.[62]

The reliability of this evidence will depend, in part, on the extent to which changes after the transaction date can be reflected in the FMV at the valuation date. During the interim period, for example, value could be affected by changes in market conditions or the project’s status, such as the receipt of permits, resolution of geological uncertainty and progress in construction. In Bilcon, there were no material changes to project status; therefore, the tribunal relied on prices from prior transactions and adjusted for trends in industry asset values over time.[63]

Failing to account for important changes to the asset’s status or the market environment will generate an unreliable outcome. In Tethyan, the respondent’s expert proposed to adjust the claimant’s 2006 acquisition price to the valuation date in 2011. This involved accounting for changes in market conditions and country risk during the interim period.[64] The tribunal found this method reasonable in concept, stating that the ‘approach to value the project based on a past trans­action involving the very same project might generally appear plausible’.[65] However, the tribunal rejected the method, because it failed to account for the fact that ‘considerable changes affecting the value of the project occurred’ between 2006 and 2011, such as the favourable outcomes from the claimant’s significant development efforts.[66]

Conclusion

The natural resource extraction sector is characterised by large projects, often of strategic importance to the parties involved, that can give rise to substantial claims. Although the overall valuation approaches on which experts rely are the usual income, market and cost approaches, their reliable application to extractive projects requires an understanding of the industry-specific factors that drive each project’s cash flow potential, the associated risks and opportunities, and the existence of well-developed commodity markets that can provide market-based inputs into damages analyses that are not always available in other industries.

The most appropriate valuation method or combination of methods for any particular case will naturally depend on the specifics of the project involved. Nevertheless, considering the nature of the assets involved and the information typically available, our experience and review of arbitral awards suggests that the income approach is frequently relied on by experts and tribunals because it can often best capture the unique aspects of the investment at issue in many of these cases. The market approach is sometimes useful but its applicability may be limited by the lack of similarity across projects. The cost approach has been employed by tribunals in some instances but its economic relevance is limited when damages are based on the FMV standard because the FMV of extractive projects is insufficiently correlated with spending on exploration and development.


Notes

[1] Darrell Chodorow and Florin Dorobantu are principals and Fernando Bañez is an associate at The Brattle Group.

[2] UNCTAD, World Investment Report 2020 – International Production Beyond the Pandemic, 16 June 2020, p. 19, https://unctad.org/en/Pages/DIAE/World%20Investment%20Report/World_Investment_Report.aspx (last accessed 7 September 2022).

[3] International Council on Mining & Metals, Role of Mining in National Economies: 5th edition, 2020, p. 22, https://www.icmm.com/website/publications/pdfs/social-performance/2020/research_mci-5.pdf (last accessed 7 September 2022).

[4] TMX Group Limited, https://mining.tsx.com/ (last accessed 7 September 2022).

[5] World Investment Report 2022: International Tax Reforms And Sustainable Investment, Box I.1., p. 4, https://www.unctad.org/system/files/official-document/wir2022_en.pdf (last accessed 3 October 2022).

[6] Venezuela alleged that the Rusoro’s mining practices jeopardised the ability to meet production targets, causing a loss to the state, which was dismissed for lack of jurisdiction. Rusoro Mining Ltd. v. Bolivarian Republic of Venezuela, ICSID Case No. ARB(AF)/12/5, Award, ¶¶ 598–610 and 897, 22 August 2016 (Rusoro). Ecuador made a successful counterclaim against Perenco for environmental damages. ‘Both sides win damages in Ecuador oil block dispute’, Global Arbitration Review, 29 September 2019, https://globalarbitrationreview.com/article/1208842/both-sides-win-damages-in-ecuador-oil-block-dispute (last accessed 7 September 2022).

[7] UNCTAD, Investment Dispute Settlement Navigator, data as at 31 December 2021, available at https://investmentpolicy.unctad.org/investment-dispute-settlement (last accessed 7 September 2022). The count excludes disputes involving downstream and support activities.

[8] T Fisher and S Perry, ‘Colombia liable in high-mountain mining dispute’, Global Arbitration Review, 13 September 2021 referring to Eco Oro Minerals Corp. v. Republic of Colombia, ICSID Case No. ARB/16/41. The tribunal has not decided on quantum yet.

[9] S Perry, ‘UK oil company wins ECT award against Italy’, Global Arbitration Review, 24 August 2022; S Perry, ‘How Italy’s ban on offshore drilling fell foul of the Energy Charter Treaty’, Global Arbitration Review, 26 August 2022, referring to Rockhopper Italia SpA, Rockhopper Mediterranean Ltd and Rockhopper Exploration Plc v. Italy, ICSID Case No. ARB/17/14. The tribunal ordered Italy to pay €190 million plus interests.

[10] T Fisher, ‘Reactions roll in to ECT modernization’, Global Arbitration Review, 29 June 2022. A draft of the ‘agreement in principle’ was published in September 2022. See N Lavranos, ‘Comment: Will successful revision talks save the Energy Charter Treaty?’, Borderlex, 19 September 2022.

[11]World Investment Report 2020 – International Production Beyond the Pandemic, 16 June 2020, p. 17.

[12] London Court of International Arbitration (LCIA), 2021 Annual Casework Report, p. 9, https://www.lcia.org/lcia/reports.aspx (last accessed 7 September 2022).

[13] Independent Petroleum Association of America, International Dispute Resolution, 2011, p. 1, https://www.ipaa.org/wp-content/uploads/2016/12/IPAA_DisputeResolution2011.pdf (last accessed 7 September 2022).

[14] F De Beaupuy and E Mazneva, ‘Russia’s Gazprom Halts Gas Supply to France’s Engie Over Compensation Dispute’, Bloomberg, 31 August 2022.

[15] Ernst & Young LLP, Spotlight on oil and gas megaprojects, 2014, p. 3, https://www.ey.com/Publication/vwLUAssets/EY-spotlight-on-oil-and-gas-megaprojects/$FILE/EY-spotlight-on-oil-and-gas-megaprojects.pdf (last accessed 7 September 2022).

[16]Investment Dispute Settlement Navigator. The Yukos entry includes three arbitrations heard in parallel that resulted in a single award: Hulley v. Russia, Yukos Universal v. Russia and Veteran Petroleum v. Russia. Amounts exclude pre-award interest. The statistics exclude cases that reached settlement before an award was issued.

[17]Vale S.A. v. BSG Resources Limited, LCIA Arbitration No. 142683, Award, ¶ 996, 4 April 2019. Amount excludes interest.

[18] Average figures are substantially higher than those in non-extractive cases for both oil and gas and mining, being influenced by the large amounts listed in Table 1.

[19] Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards on Mineral Resources and Reserves, adopted on 20 May 2014 (CIM Definition Standards); Petroleum Resources Management System (PRMS), revised June 2018. Definitions can vary across jurisdictions but they have much in common given the global nature of the sector.

[20] ‘Figure 1, Relationship between Mineral Reserves and Mineral Resources’ from the ‘CIM Definition Standards – For Mineral Resources and Mineral Reserves’. Reproduced with the permission of the Canadian Institute of Mining, Metallurgy and Petroleum.

[21] ‘PRMS, Figure 1.1’ reproduced with the permission of the Society of Petroleum Engineers. In this figure: 1P = proved reserves, 2P = proved and probable reserves; 3P = proved, probable, and possible reserve; 1C to 3C refer to contingent resources estimated with varying degrees of certainty from high to low; and 1U to 3U refer to prospective resources, also estimated with varying degrees of certainty.

[22]Burlington Resources Inc. v. Republic of Ecuador, ICSID Case No. ARB/08/5, Decision on Liability, ¶ 432, 14 December 2012.

[23] In the ex ante approach, the expropriated asset is valued at the expropriation date and then that amount accrues pre-award interest until the award date. In the ex post approach, the expropriated asset is valued at the date of the award (or the hearing, for practical reasons).

[24] See, e.g., Glencore International A.G. and C.I. Prodeco S.A. v. Republic of Colombia, ICSID Case No. ARB/16/6.

[25] F Dorobantu et al, ‘Country Risk and Damages in Investment Arbitration’, 31(1) ICSID Rev. 219–31 (2016).

[26] See, e.g., R Davis et al, ‘Costs of Company-Community Conflict in the Extractive Sector’, Corporate Social Responsibility Initiative Report, No. 66, 2014.

[27]Bear Creek Mining Corporation v. Republic of Peru, ICSID Case No. ARB/14/21, Award, ¶ 600, 30 November 2017.

[28] Social licence risk is also a key issue in the ongoing Gabriel Resources v. Romania, ICSID Case No. ARB/15/31, which has seen expert testimony on the issue. See Claimant’s Reply and Counter-Memorial on Jurisdiction, 2 November 2018, pp. 18–19 and Respondent’s Rejoinder, dated 24 May 2019, p. 9, available at https://www.italaw.com/cases/4721.

[29] The CIMVAL Code for the Valuation of Mineral Properties, prepared by the Special Committee of the CIM on the Valuation of Mineral Properties (CIMVAL Code), 29 November 2019; an earlier version was published in 2003.

[30] CIMVAL Code, ¶ 3.3.3.

[31] VALMIN 2015, § 8.8. The VALMIN Code was first adopted in 1995.

[32] SAMVAL 2018, § 4.4. The SAMVAL Code was first adopted in 2008.

[33] Society of Petroleum Evaluation Engineers, Perspectives on the Fair Market Value of Oil and Gas Interests, 2002.

[34] International Valuation Standards Council, International Valuation Standards 2017, at 42–43 (¶ 60.1) (2017).

[35] For a detailed discussion of the cost approach to valuation, see Guide to Damages in International Arbitration, 4th Edition (Global Arbitration Review).

[36] See, for example, Crystallex v. Venezuela, ICSID Case No. ARB(AF)/11/2 (Crystallex), Award, ¶¶ 877–85 and Tethyan Copper Company Limited v. Islamic Republic of Pakistan, ICSID Case No. ARB/12/1, Award, ¶¶ 309–35 (Tethyan). The income approach, and its most frequent implementation (the discounted cash flow (DCF) method), has also become standard in arbitrations involving other industries. See, for example, Watkins Holdings S.à r.l. and others v. Kingdom of Spain, ICSID Case No. ARB/15/44, ¶ 694, as one of the cases concerning claims arising out of a fundamental revision of the regulatory regime and reduction in the level of support to renewable energy in Spain.

[37] Based on the authors’ review of publicly available awards in cases listed in UNCTAD IDSN. Not all the cases involved project valuation questions.

[38] See, e.g., E Schwartz, et al, ‘Short-Term Variations and Long-Term Dynamics in Commodity Prices’, Management Science 46(7), 2000, pp. 893–911; D Laughton, et al., ‘Reversion, Timing Options, and Long-Term Decision-Making’, Financial Management 22(3), 1993. As project lives often exceed the horizon for which derivative contracts are listed, long-term projections can be developed using economic models of price evolution, calibrated using historical market prices.

[39] For example, the US Energy Information Administration publishes long-term forecasts for crude oil prices in its Annual Energy Outlook (see https://www.eia.gov/outlooks/aeo/ (last accessed 3 October 2022)) and the World Bank publishes forecasts across a range of commodities in its quarterly Commodity Markets Outlook (see https://www.worldbank.org/en/research/commodity-markets (last accessed 3 October 2022)). Many investment banks also publish commodity forecasts.

[40] R Brealey, S Myers and F Allen, Principles of Corporate Finance, 10th edition, pp. 223–27.

[41] Systematic risks are those risks that cannot be eliminated by holding a diversified portfolio of investments because they affect all assets to some degree. See Brealey, Myers and Allen, op. cit. note 39, above, Chapter 10.

[42] For a primer on commodity prices, see R Pyndick, ‘The Dynamics of Commodity Spot and Futures Markets: A Primer’, The Energy Journal, 2001, 22(3), p. 1–29.

[43] The main source of market risk in a natural resource project is the price risk, which affects the revenue stream. Cost elements, however, can also incorporate systematic risk elements; e.g., in mining, fuel costs can be a substantial portion of costs. Fuel costs are correlated with crude oil prices, which have recently shown increasing correlation with overall markets, and hence increased systematic risk.

[44] The certainty-equivalent DCF method, labelled the ‘real options’ method when combined with the ‘real options’ element described below, is listed as a primary method in the CIMVAL Code (¶ 3.3.4). See also CIMVAL Letter in response to International Valuation Standards Council Re: Valuations in Extractive Industries – Discussion Paper, 22 October 2012.

[45]Tethyan, Award, ¶ 360, 12 July 2019.

[46] If comparable assets did not trade at similar prices, market participants would be able to generate a profit through arbitraging the price differential, which would cause the difference to disappear or become minimal.

[47] EBITDA (earnings before interest, taxes, depreciation and amortisation) is a proxy for operating cash flow.

[48] VALMIN Committee,VALMIN response to the [International Valuation Standards Council] IVSC Discussion Paper, 11 July 2012, p. 2, https://www.ivsc.org/files/file/download/id/333 (last accessed 7 September 2022).

[49]Copper Mesa Mining Corporation v. Republic of Ecuador, PCA No. 2012-2; Crystallex; Gold Reserve Inc. v. Bolivarian Republic of Venezuela, ICSID Case No. ARB(AF)/09/1 (Gold Reserve); Khan Resources Inc. et al. v. Gov’t of Mongolia & MonAtom LLC, PCA Case No. 2011-09 (Khan Resources); Rusoro; and South American Silver Limited v. Bolivia, PCA Case No. 2013-15 (South American Silver).

[50]Crystallex, Award, ¶ 902. Many gold projects produce other metals, such as copper. To adjust for mix differences, some analysts convert reserves of secondary metals into their value equivalent in terms of ounces of gold, or ‘gold-equivalent reserves’.

[51]Crystallex, Award, ¶ 902.

[52] ibid., at ¶ 907.

[53] ibid., at ¶ 909.

[54]Gold Reserve, Award, at ¶ 831.

[55] ibid., at ¶ 832.

[56]Copper Mesa, Award, ¶ 7.24; Khan Resources, Award, ¶¶ 398–99; Rusoro, Award, ¶ 782; South American Silver, Award, ¶ 843.

[57]Occidental Petroleum Corp. & Occidental Expl. And Prod. Co. v. Republic of Ecuador, ICSID Case No. ARB/06/11, Award, ¶ 787, 5 October 2002.

[58] See, e.g., BofA Merrill Lynch, Global Gold & Precious Metals, 9 April 2013, https://www.merrilledge.com/publish/content/application/pdf/gwmol/GlobalGoldandPreciousMetals.pdf (last accessed 7 September 2022), pp. 93–94; Ernst & Young LLP, Golden Queen Mining Co. Ltd. Formal Valuation and Fairness Opinion, 1 April 2019, p. 18, https://www.sec.gov/Archives/edgar/data/1025362/000127956919000874/tv518695_ex99-1.htm (last accessed 7 September 2022).

[59]Gabriel Resources Ltd et al v. Romania, ICSID Case No. ARB/15/31, Claimants’ Memorial, 30 June 2017, ¶¶ 922–93, https://www.italaw.com/sites/default/files/case-documents/italaw9821.pdf (last accessed 3 October 2022).

[60] The Crystallex tribunal rejected the P/NAV method as implemented, but stated that: ‘the Tribunal considers that conceptually it would have no difficulties in accepting it as a method per se’. See Crystallex, Award, ¶ 896.

[61]Khan Resources, Award on the Merits, ¶¶ 400–01 (citations omitted), 2 March 2015. The tribunal in Crystallex reached a similar conclusion; Crystallex, Award, ¶ 890.

[62]Bilcon of Delaware et al v. Government of Canada, PCA Case No. 2009-04, Award on Damages, ¶ 289 (citations omitted), 10 January 2019 (Bilcon).

[63]Bilcon, Award on Damages, ¶¶ 295, 297, 298 and 302. The tribunal recognised the need to adjust an offered purchase price downwards because it was conditional on receipt of permits that had not been granted by the valuation date.

[64]Tethyan, Award, ¶ 1695. Specifically, the adjustments were for changes in metals prices, global mining costs, the cost of capital for metals mining, and Pakistan’s country risk.

[65]Tethyan, Award, ¶ 1725.

[66] ibid., at ¶¶ 1726–39.